Metropolitan Water Treatment Facility

Industry
Public Sector - Waste Water Utility
Software Package(s)
Lawson Financials and Procurement
Background
The client is a mid-size sewage treatment facility (250 Employees) servicing 28 communities in Milwaukee County. They needed an experienced project manager to work with their staff and the software implementers for the successful delivery of this project.
Challenge
The client was moving to an ERP based solution that included the latest advances in information technology to improve organization-wide decision support. Prior to this endeavor, most of the Client’s requirements were completed through in-house custom development.
Solution
We provided a project manager with over 4 years of ERP implementation experience and over 17 years of business experience including CPA certification.
Result

Our Project Manager provided the following:

  • online PO approval to improve efficiency and accuracy
  • budget edits to help manage operations and reduce total effort
  • real-time project accounting capabilities improving responsiveness for corrective action to variance